Dear all,

I have given machine,labour time is 2 mins for each in routing.

But during confirmation its showing different mins.I have not done any settings.

Kindly find below image,please clarify

Regards

Rajasekaran

Accepted Solutions (1)

Accepted Solutions (1)

Anupam1143
Active Contributor
0 Kudos

Hi,

In routing you maintain activities values just for the base qty for operation and when you do the confirmation system calculates on the basis of yield or confirmed qty, based on the configuration settings for confirmation parameters.

So these values will always be different from routing base qty until you confirm the same base qty in CO11N/CO15.

Regards,

Anupam Sharma

former_member1241202
Active Participant
0 Kudos

Hi sharma,

In routing for base quantity i have given 2 mins.

During confirmation yield quantity 2,so its has to come 4 mins,but its showing some different value

Regards

Rajasekaran

Anupam1143
Active Contributor
0 Kudos

Hi

Check the formulas which you have assigned to machine/Labor in work center, you can also test the formula in work center it self, also check whether you have assigned operation splitting in routing.

Regards,

Anupam Sharma

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Raja

Analyzing the screenshots, it looks like the times in the routing are in minutes but the times on the confirmation are on a different unit of measure.

Which unit has been defined for the standard value on the order operation?

BR

Caetano

Answers (1)

Answers (1)

former_member1241202
Active Participant
0 Kudos

Dear Caetano,

Thanks for your valuable suggestions.

BR

Rajasekaran