Problem during Process Order Confirmation - COR6N

Dear All,

We are into process industries

Till now we are creating different BOM for each section and different process orders for each BOM.

For example Pulverize, Acid MIXING, Continuous Rotery, Blending and Packng.

Now we have created new BOM for FG - showing all input/output of RM, SFGs. In Recipe, define operation for each section. and assign operation to material. I have attached screenshot of Recipe Operation.

During process order confirmation, system shows movement type of all material perfectly during each phase. But during confirmation of last phase system does not show 101 movemet of FGs.

I have checked in Recipe, control key is ok i.e. Automatic GR, in OPK4 setup is also correct.

We have created new BOM and Recipe. There is no change in other configuration parameter.

Thanks and Regards,

Nirav

Recipe.JPG (100.3 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Jun 04, 2014 at 01:57 PM

    Hi Nirav

    The automatic goods receipt is defined by the operation/phase control key.

    Control key PI03 has the automatic goods receipt setting by defaul.

    Analyzing the screenshot I could observe that this control key is assigned to all the opration/phases, however, it should only be assigned to the last operation/phase, where the goods receipt will actually take place.

    For all the previous operations/phases you should use a different control key, without automatic goods receipt, such as PI01.

    BR

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Caetano,

      Yes you are correct.

      I was doing mistake. I belive that to show by-product 531 movement PI03 is required.

      In 0040,0060 and 0080, we kept stock at SFG level. So we need to show 531 movement.

      Now I have change PI01 at all phases and PI03 at last phase 0100. Now it is ok.

      Thanks and Regards,

      Nirav

  • Posted on Jun 04, 2014 at 01:30 PM

    Hi Nirav,

    are you getting any error message. did you check COGI. check weather the goods recipt storage loction is maintaine d or not.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.