Has anyone successfully implemented first artlicle inspection during manufacturing ?

Also during purchase order receipt we can have first article inspection via the Q info record. This workss fine to have the 0101 inspection type for teh first article. However if the first article inspection lot is not dispositioned, the system does not allow me to receive subsequent lots.It says "No inspection lot can be opened for vendor and material". Is it possible to allow the system to allow subsequent receipts to take place though the first article is open ?

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Jun 03, 2014 at 03:53 AM
    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      I have seen that and know it very well.....I have set up first article inspection for purchase receipts. I am asking about manufacturing inspections first article. Plese read my post carefully. Also the receiving first article inspections blocks subsequesnt receipts (again...read my post carefully) until it is dispositioned. I want first artcle which is still open to allow me to receive further lots.

  • author's profile photo Former Member
    Former Member
    Posted on Jun 03, 2014 at 04:42 AM

    In configuration remove status, create an inspection lot and try. I am not sure this will work, but try once.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 04, 2014 at 09:25 AM

    Hi GS,

    What do you mean by first article inspection during manufacturing ?


    You create first production order for a material (SFG/FG) and completes the production order make the GR..stock goes in to quality with inspection lot generation..Now till the time this first inspection lot is cleared system should not allow create/release the second production order for the same material..

    is this the requirement ????..

    if yes... then it is not possible in standard SAP...you need to go for some enhancement...

    if no...elaborate your requirement in detail...


    Thanks

    Kumar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.