on 01-30-2017 1:59 PM
If I receive 100 bags and 20 bags are sent out to the lab for destructive testing,
How can I setup MRP to be aware of this when it generates PREQs?
Sometimes there are multiple PREQs EX: I have a Order for 2 Orders for 100pcs I would need 240 bags because 40 would be send to the Lab...
Please help me on what I need to do in MM to set this up
- Thank You OMS216