CC line items

hi

I have a created contract PO but I can not see any committed line items on the cost center (KSB2) or on the project level (CJI5).

can anyone help me?

thanks

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 03, 2014 at 03:15 AM

    Hi,

    Did you activate the commitment update in the CO area config?

    Regards

    Ali

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 03, 2014 at 04:46 AM

    Hi Michael

    1. You need to activate Commitment Management in Controlling Area

    2. you need to activate it in the Cost Center and the Project profile

    COmmitments are by default active in CC, unless you lock them in the CONTROL Tab

    Br. Ajay M

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.