To manage Purchase requisitions and to effect a stock transfer from DC (texas) to customer location (florida) what are the config setting I do in SNP

That is florida customer is purchasing directly from texas.

Using /SAPAPO/TL I can create a transportation lane.using source and destination fileds.that much I know ,what should I do in SNP1 and SNP2 tab in MAT1.? And what should I do in product location screen ,there I find a procurement tab there ..what config should I do there.if you have tried a similar SNP task before please share with me.I will try at my end according to my scenario.basically a stock transfer should be effected from texas to florida for a price.that is the crux of the matter

thnaks

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 02, 2014 at 04:09 PM

    The advice above is correct but is only setting up the master data, what method do you plan to use to create the STR (Purchase Req)? Are you planning on APO SNP creating the purchase req based on demands? if so your question is very broad and what you mean to ask is how to set up an SNP solution. Eg, Heuristics / CTM/ Optimiser.

    But I think you are asking how to manually create the STR?

    Please let me know if you have details questions and I can try to help.

    S SB

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      that is i am using SNP hiuristics ...rite...now when i run SNP hiuristics it should create a procurement type of category stock transfer...and that stock transfer has to moved to a location at lower cost (cost settting has already been made by previous implementor...now it is a re-implementation project) in the SNP hiuristics screen we have one tab called "network " the client says once i press that SNP hiuristic network label ....ST should occur automatically...ie there should be zero manual intervention ..all automatic...once MC90 release happens to SNP..SNP hiuristic should take care of everything....demand is FC demand and customer demand .....SNP should handle customer demand seperately and FC demand seperately....i agree my question is broad..it is best you please suggest some links that carries screen shots....that would be a grt help to me mani

  • Posted on Jun 01, 2014 at 06:08 AM

    Hi,

    Hope you have already maintained Florida as the location in APO.

    Then you create the material in Customer location. You can use the same settings as they are in your DC (Texas) and make sure that the procurement type is F in Florida.

    Then you assign this material to your active model 000.

    After that maintain the T-lane from DC-Texas to Florida. Make sure you maintain your product in it.

    Then you will be able to create Stock transfer purchase requisitions in Florida.

    Regards,

    Manimaran M.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      ok mani -i go to sapapo/loc3 create locations there -then i go to product -location screen maintain the product ,then create TL...hope that will solve my issue....will try it out thanks mani..

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.