on 05-29-2014 6:12 PM
Hello Gurus,
I am running MRP through batch MRP run
(t.code - wc27),
Processing key NEUPL 3 3 1 1 1. I want to create dependents requirement future dated so date input I gave is 28/12/2018 last working day form factory calender., but requirement is not created.
Please help I am new in this module. Need help.
Hello Ameya
I don't see the point of running MRP with date 28/12/2018.
Dependent requirements will be created on future date according to the parent planned order date, not to the MRP date.
Please try to run MRP again it with today date.
If you want to have dependent requirements in the future, please make sure that there are planned orders with date in the future for the parent materials.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Caetano,
Actually my client has scheduled the job for daily MRP run, so for all the sales orders they have dependents requirement is created with system date and that date is updated daily since job is scheduled so this process is scewing their production process. If MRP run is of future date then dependents requirement is also future dated and client also want requirement date to be in future.
Thanks for quick reply..
Hello Ameya,,
Not only this date 22/12/2018, but you can try with 27/12/2018, and this date also work in your case.. ( Make sure your date is working day as per factory calendar)
Normally MRP/MPS batch job run in night after factory shutdown for this reason system not generated requirement on last working days.
Regards
Umesh Mali
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.