TDMS - System Analysis Phase completed with errors

Hi All,

We are running TDMS copy, currently running at System Analysis phase, however we encountered status message "completed with error" within sub-step "Generation of Run-Time Objects for Data Transfer". When we checked the tasks, we found below error messages...

Error while generating runtime objects for ZJ_3RFREP_VALFMT_01W

Syntax error in function module /1CADMC/OLC_950000000614930

Error message: Type "DECFLOAT16" is unknown

We tried re-executing the step several times but no success.

Can anybody suggest how to fix the issue. Thanks.

Regards,

Philip

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on May 29, 2014 at 04:20 PM

    Hi experts,

    We opened an OSS incident regarding this issue, and SAP responded to exclude the migration object J_3RFREP_VALFMT from the current transfer using the troubleshooter.

    However, while we execute the troubleshooter, message prompt "Activity 'Troubleshooting for Migration Objects' execution 0003 in package 9002D, phase 'System Analysis' has been aborted ." appears.

    In the Phase Overview of the System Analysis, step "Troubleshooting for Migration Objects" is added, which has an aborted status. Checking the logs of that steps we found below.

    Skip Migration Objects from Current Transfer

    I EQ J_3RFREP_VALFMT

    Destination to the central system is not created yet

    We checked all the RFC connections and all seems working fine.

    Can anyone share how to fix this or what to check further.

    Regards,

    Philip

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi anita,

      Thanks for the response.

      The error appears to be fixed for us by implementing below...

      - sap notes based on 1741455 - TDMS 4.0 - Basis Composite Note.

      - SAP Notes 1965713 and 1973799

      System Analysis completed, however, the phase runtime took 1 day to complete.

      Our concern now is, can anyone share how can we optimize this runtime.

      Regards,

      Philip


Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.