Dear all,

Kindly please let me know what are the settings to be made for automatic batch creation while creating production order.

Regards

Rajasekaran

Accepted Solutions (1)

Accepted Solutions (1)

former_member1241202
Active Participant
0 Kudos

Dear Joy,

Find below image,in previous period some of the stock available how to view and cancel that stock.

I have one doubt pls let me know,if stock is available whether Automatic batch will create or not?

Regards

Rajasekaran

dejoy
Active Contributor
0 Kudos

If you are able to on batch management indicator than automatic batch creation will happen.Consult your MM for this correction and you may check    as well for reference.

Regards,

former_member200568
Active Participant
0 Kudos

For batch management all the stock should be zero.

Because of previous period stock, system is not allowing you to do batch management.

please do the following activity.

1) Make the current stock of SLOC  as same as previous stock by uploading through mb1c 561 mvt. with posting period as current period .

2) Now the current = previous stock.

3) Now do mb1c ----> 562 mvt ------>  remove same stock as you uploaded & keep posting period as previous period.

4) Now stock will be ZERO in both the period.

5) Now Activate the Batch Management tab from purchasing view in material master  MM02.

Now we have to upload the previous stock as it was earlier.

6) Upload the stock which was removed from the previous period by mb1c----> 561 mvnt-----> keeping posting period as previous period. ( assign the batch )

7) Now current stock = previous stock.

😎 again remove stock from the current period by mb1c----> 562 mvt-------> posting date as current date.


Hence your material will be batch managed & stock condition will remain same as it was earlier.

( need bit of concentration while doing above said activity.

#Reward points if found useful.

Regards,

Deep Dave.

Answers (7)

Answers (7)

former_member1241202
Active Participant
0 Kudos

Dear Deep,

Thanks for your valuable suggestion.I have done as per your reply,now stock become zero and batch created automatically.

Regards

Rajasekaran

former_member200568
Active Participant
0 Kudos

Please close the thread by selecting correct or assumed answers tab. as it will clear the picture to other users.

Regards,

Deep Dave.

dejoy
Active Contributor
0 Kudos

Hello Rajasekaran,

Glad that helped but i noticed that helpful/correct answers does not match to the primary question.

Regards,

former_member1241202
Active Participant
0 Kudos

Dear Joy,

  • I checked in MMBE stock is not available.
  • How to check if material lies in previous period or not?

Regards

Rajasekaran

dejoy
Active Contributor
0 Kudos

Check in material master-storage loc stock view.Here check what lies in previous period.

Regards,

former_member1241202
Active Participant
0 Kudos

Dear Joy,

Whether classification should be maintained for raw material and finished goods?

Regards

Rajasekaran

dejoy
Active Contributor
0 Kudos

Dear Rajasekaran,

It depends on your requirement.If business needs to classify nay kind of material than go for it.Hope its clear.

     By the way did you check stock lies in previous period or not?

Regards,

former_member1241202
Active Participant
0 Kudos

Dear Joy,

While selecting Batch management in work scheduling.

It shows display error

But stock is not available for this material in stg location 0001

Regards

Rajasekaran

dejoy
Active Contributor
0 Kudos

Please check carefully in MMBE,may be having stock in other stock type.?If you are testing than test with  any new material.

Regards,

dejoy
Active Contributor
0 Kudos

Please check stocks in previous period too.

Regards,

former_member1241202
Active Participant
0 Kudos

Dear all,

  • I have done the customization in OPKP and CORW.
  • But find below image still its showing material not handled by batches

Regards

Rajasekaran

dejoy
Active Contributor
0 Kudos

Please maintain "Batch management " indicator in material master work scheduling view.

Regards,

dejoy
Active Contributor
0 Kudos

Hello Rajasekaran,

use CORW and make settings as below.

and assign this profile to material master-work scheduling view.

Regards,

Former Member
0 Kudos

Hi,

You can specify in the production scheduling profile if batches will be created when the production order is released or created. Production scheduling profile is customized under Production->Shop Floor Control->Master Data, transaction code is OPKP. After creating a new profile you need to assign the profile to materials. You might as well assign the profile to production schedulers and assign production schedulers to materials.