Acivity Scheduled

amogh_kashyap
Explorer
0 Kudos

Hi ,

can anybody let me know when does scheduled activity values gets populated in KP26 transaction.For some of the periods in KP26 against few activity type its getting populate for few its not populated.new to controlling.

Accepted Solutions (1)

Accepted Solutions (1)

rajneesh_saxena
Active Contributor
0 Kudos

Dear Amogh

This is populated from Long term planning (LTP) in PP. This schedule you can compare with you plan and update in the plan column using KPSI.

Regards

Rajneesh Saxena

amogh_kashyap
Explorer
0 Kudos

Hi Rajneesh,

Thanks for your reply but my issue is need to migrate cost center plan data from one sap system to another .Though have uploaded activity plan data using KP26 in new system.But the scheduled activity value is not having in KP26 screen for new system if i compare it with the old system having values.Hence need to know that is there any step which i might be missing.

Regards,

Amogh

rajneesh_saxena
Active Contributor
0 Kudos

Dear Amogh


Long Term planning (LTP) is a process which is handled by PP and CO both in conjunction. In this based on the production plan system calculates activity requirement to do that planned production. This is called scheduled activity. Then From PP this plan is transferred to CO and there this schedule is compared with planning. Following are the steps involved. Out of them few may not be used in your case depending upon the process.


1  Update planning scenario (MS32)

           2. Check or change manually the production volume (MD62) 

           3. Execute Long-Term-Planning  (MS01)   .

           4. Transfer activities to cot centers (KSPP)

           5. Plan reconciliation after (KPSI)

6 Activity dependant or Activity independant planning

7 Planning SKF (KP46) (if you are using)

8 Manually planning of labour hours (KP06)

9 Calculate Labour activity prices (KSPI)


hope this may help you.


Regards


Rajneesh Saxena

rajneesh_saxena
Active Contributor
0 Kudos

Dear Amogh

I suggest you to wait for other experts opinion to continue further. On your behalf would like to invite Sir to make comment on this.

Because after writing suggestions I myself is little confused on completeness of the process. So please wait for experts.

Regards

Rajneesh Saxena

ajaycwa1981
Active Contributor
0 Kudos

Hi Amogh

The mentioned process is correct and complete

Scheduled activity is updated when you do KSPP

Br. Ajay M

amogh_kashyap
Explorer
0 Kudos

Hi,

thanks @Ajay Maheshwari - SAP Trainer  and @Rajneesh Saxena  client want to have cost centre plan data to be migrated to new system so was just following KP06 and KP26 to update values now with the appropriate steps will be able to do migration properly.

Thanks a lot

Regards,

Amogh

rajneesh_saxena
Active Contributor
0 Kudos

Many many thanks Ajay Sir.

High regards

Rajneesh Saxena

rajneesh_saxena
Active Contributor
0 Kudos

Great Amogh.

Now I am sure you will achieve your goal.

Rajneesh

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Amogh,

I'm not aware of any way you can "manually" update "Scheduled Activity" field.

Seems like like "Scheduled Activity" field is only updated via txn. KSPP.

But that of course requires LTP, SOP and the rest.

You may need to create your own program to achieve what you want.

Thanks,

Szymon