Hi Gurus
I hope one of you Guys / girls can help me or point me in the right direction
In MB21 Mov.type 311 we create reservations on materials that are normally MTO Stock. This Means that the reservation will create a plan order when the MRP is run onthose materials. This is all ok, but if we have 2 - 3 reservations on the same material SAP standard is to create one plan order for the number og materials missing in order to cover the 3 reservations.
In the picking process one employee will pick the entire reservation, including the MTO which is basically a BOM for picking ( screws, botls, bearings etc etc )
The reason we use mov.type 311 is the each reservation are to be moved to another storage location that is physical Places elsewhere, but not defined as a warehouse.
Is it at all possible til have the MRP create a planorder for each reservation ?
Kind regards
Jens Olsen
Denmark