on 05-27-2014 12:23 PM
Hi Gurus
I hope one of you Guys / girls can help me or point me in the right direction
In MB21 Mov.type 311 we create reservations on materials that are normally MTO Stock. This Means that the reservation will create a plan order when the MRP is run onthose materials. This is all ok, but if we have 2 - 3 reservations on the same material SAP standard is to create one plan order for the number og materials missing in order to cover the 3 reservations.
In the picking process one employee will pick the entire reservation, including the MTO which is basically a BOM for picking ( screws, botls, bearings etc etc )
The reason we use mov.type 311 is the each reservation are to be moved to another storage location that is physical Places elsewhere, but not defined as a warehouse.
Is it at all possible til have the MRP create a planorder for each reservation ?
Kind regards
Jens Olsen
Denmark
Hello Jens
If the reservations have all the same date, MRP will always create a single replenishment proposal, even if you are using lot sizing procedure EX.
See question 6 of the FAQ note 550568:
6. Question:
There are several requirements on one day. Is it possible that the
MRP creates a separate procurement proposal for every requirement?
Answer:
Same as for the daily lot size with a number of periods = 1 (lot
size TB), requirements of one day are also grouped into one
procurement proposal for the lot-for-lot order quantity (lot size
EX) (see documentation for the lot-for-lot order quantity). Separate
procurement proposals can be achieved only if you work with
make-to-order production. Here, the requirements are managed in
separate planning segments of the stock/requirements list.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Caetano
I can see the logic in that, and thank you for finding the note for me.
It would be great if i could atleast get 1 requrement for each storage location, but the plan order is only doing what it is surposed to do ..
I will try to figure out another way to handle these if at all possible.
BR
Jens
Hi Jens
If you have requirements from different storage locations, you can use a setting called "storage location planned separately". You can find that on tab MRP4 of material master if you enter using the plant and the storage location.
That way, requirements from different storage locations will be planned separately and different procurement proposals will be created for each one.
BR
Caetano