HI Guys,
we are maintaining the activity price in KP26 for mandays activity and confirming it in IW41. Now if activity price is not maintained in KP26, and confirming the mandays in IW41, system should through an error message. please let me know how can i do this.
Anil Kumar. V
Anil Kumar. V
I have used one of the confirmation user-exits to make these checks (CONFPM* via SMOD).
From memory I started the warning messages 3 months prior to the KP26 values expiring.
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
you can check the SPRO in Define Control Parameters for Completion Confirmations where you can mark the Actual cost , and Termination for incorrect act cost. where in it will through an error which confirming the same.
If the above conditions don't met your requirement you can check the same using user exit
Regards
Thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.