Skip to Content
0
Former Member
May 25, 2014 at 10:34 AM

Planned Replenishment with Message no. /SCWM/REPL008

624 Views

Hi experts

I can run Planned Replenishment with the old material and system can created the warehouse task. but for the new product created today, after excuted the REPL program and it shows the related replenishment quantities, but when click "perform replenishment" system alway says "Replenishment run started in whse no. W202 with replenishment strategy Planned Replenishment. Message no. /SCWM/REPL008". I have compared the product parameters and they are same, some backgroud as below:

1, I use the consign stock for vendor,

2, have assigned the fix bins to the new material.

please advise.

Leo