CN41N and S_ALR_87013533 report not showing Production order planned cost

Hi Experts,

I am having issue to get total planned production order values in my CN41N or S_ALR_87013533 cost report. I am facing 2 issues :

1. CN41N repoet does not show individual material cost planned in BOM.

2. CN41N report and S_ALR87013533 report does not show total value but only picking fixed value.

Example :

1. CN41N report :

Above screenshot shows no values in Project plan cost & Order cost column but it shows total cost as a lumpsum on top for project. I need to know how can i get material cost populated here for Project Valuated stock material?

2. S_ALR_87013533

This report shows Total Cost of BOM as 1 line under Material Procurement activity similar to CN41N report. Also Order value is picking from Fixed cost from planned order and total cost is added on top. How can i get Total cost picked from production order?

Is there any Setting in PS config which allow me to pick the detail production order plan cost in both report under planned cost.

Thanks in advance.

Ashish

CN41N.jpg (286.4 kB)
S_ALR87013533.jpg (241.7 kB)
Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    Posted on May 23, 2014 at 10:10 AM

    Hi Ashish,

    Please check in OPSV settings . Both the check boxes are ticked for PP order type or not.

    Check mark these check boxes followed by CJEN run and check the report again.

    Regards

    Saurabh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 28, 2014 at 05:13 AM

    Hi Experts,

    Kindly suggest what is required to be done as this issue is not resolved yet.

    Thanks a ton in advance

    Ashish

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 09, 2014 at 08:27 AM

    Hi Ashish,

    Have you got any success on it?

    Regards

    Saurabh

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Sudhakar,

      I highly appreciate you reply to provide me the pointers

      S_ALR_87013533 gives me production order wise cost but not the actual cost of material (raw mat/ consumables) consumed in production.


      S_ALR_87013542 can not see (raw mat/ consumables) cost by material consumed in production.


      CJI3 report is useful which i have already considered as option however for my project CN41N report is the main report and i have a requirement if i can bring those details in CN41N.


      Thanks for all the help.


      Ashish


Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.