Dear All,

The budget is 1500 USD. The PO was created with an amount of 1000 USD and kept down payment as 250 USD . So the balance is 500 USD. While making down payment through ME2DP, system will bring FM objects from PO against advance line item. After this step, the commitment will reduce from 1000 USD to 750 USD. If any user enters expenditure directly in FI by using the same budget code, system will allow for the remaining amount 750 USD. When we are doing service entry sheet against this PO for full amount 1000 USD then system is giving error message as budget exceeded by 250 USD. This is due to commitment reduced while making down payment. We used the derivation rule based on transaction type to overwrite the commitment but system is bringing commitment field value from PO at the time of posting.

Please give us the solution to avoid reducing the commitment while making down payment with reference to PO.

Update profile: 000101

Value Type: 61 (Statistical Update)

Regards,

Sree

2 REPLIES 2

JavedKamal
Active Contributor
0 Kudos

Hi Sree,

You need to check or Configure Automatic clearing of Down Payments, please check the IMG setting:

Public Sector Management>Funds Management Government>Actual and Commitment Update/Integration>Integration>Configure Automatic Clearing of Down Payments/Down Payment Requests:

Activate check box "DP Clr" down payment clearing during a GR/IR

If this flag is set, the down payment is cleared automatically during the creation of the goods receipt (GR) or invoice receipt (IR), depending on your FM settings.

Regards
Javed

0 Kudos

Hi,

Thanks for your information. We have done these settings previously as you suggested. The budget is consuming at the time of Invoice because GR/IR account is updating budget consumption report for invoice document but is not updating GR/IR line item for Goods receipt entry in budget consumption report. So its consuming budget twice due to GR/IR line item. We hope the problem is due to package level. Now we are trying to upgrade package.

In mean time, we are processing down payment with reference to PO then its reducing commitment to the extent of down payment.

Regards,

Sree