Skip to Content

Not all transports request yet released - CHARM status change to pass to test

Hi,

We have implemented CHARM for our ECC landscape DEV/QAS/PRD and solution manager 7.1 SPS10.

Once the request for change is created and approved and released for development. Developer puts it in development and once the development is complete when he is trying to "PASS changes to test" the process runs for some time and gives the following message.

"Not all the transport request yet Released"

"Status was reset by System"

But when I check all the task under the transport request are released. Once I select the "recheck transaction" and try to change the status second time to "Pass change to test" and successfully releases and import the request to QAS system.

Not sure why it is not doing the first time and second time when I am doing the recheck transaction and try again it works perfectly fine.

please help in resolving the issue.

Regards

Alam.

issuedoc.png (24.9 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

7 Answers

  • avatar image
    Former Member
    Feb 09, 2015 at 11:56 PM

    For all guys facing this or similar issue with consistency checks behaving strange - read the reply by Sid Bharadwaj above.

    It seems that there is a bug in SP10 : when copying SMMJ into ZMMJ the consistency checks execution time does not copy  - this is messing up the CHARM actions.

    Consistency checks are running in 2 steps: Regular and Final, it needs to be setup correctly for each CHARM action, but by default it is Regular.

    So just compare to SMMJ and adjust ZMMJ accordingly.

    Elena

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 22, 2014 at 06:11 AM

    Hi Alam.

    Check this

    http://scn.sap.com/docs/DOC-53781

    Regards Daniyar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 22, 2014 at 09:57 AM

    Hi Alam,

    You need to change the Execution time of the actions.

    Goto SPRO > SAP Reference IMG > SAP Solution Manager > Capabilities (Optional) > Change Control Management > Standard Configuration > Change Request Management Framework > Actions in Change Request Management -> Determine execution time of Actions.

    Here for the status "To be Tested" change the Time to "0 Execute Before Checks".

    Regards,

    Laxman

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 22, 2014 at 10:15 AM

    Hi Alam,

    This issue will arise when the TR taking more time to release the object, if the time out. will get the error warning message.

    once the CD is refresh error will disappear.


    Rg,

    Karthik

    Add comment
    10|10000 characters needed characters exceeded

    • Hello Sir,

      The task "Pass change to Test" has a below prerequisite -

      Only the child TR(s) needs to be manually released by its owner(s) in the system using transactions SE01/SE09.

      Parent TR needs to be left as-is.

      Once this is done, then try "Pass change to test", else this functionality just does not work & keeps resetting the status to In Development.

      This action releases the parent TR & imports it to QAS system.

      Also please use the refresh button located in the TR section, after releasing the child TR & before selecting task "Pass change to Test". This will save you a lot of errors related to inconsistencies.

      Also, please make sure that your user IDs in the DEV/QAS/PRD systems are same as being used in SolMan system (as Trusted RFCs are used) & have authorization for objects S_RFC & S_RFCACL. Otherwise this also causes some issues while trying to import TRs using action "Pass change to Test".

      Best Regards,

      Tanmeya

  • avatar image
    Former Member
    Aug 11, 2014 at 11:36 PM

    i am not sure how you guys fixed the issue. But i encountered the same error and on investigation i found that some entries were missing for ZMMJ.

    SPRO --> SAP Solution Manager --> Capabilities --> Change Request Management --> Change Request Management Framework --> Make Settings for Change Transaction Types --> Define Execution Time for Consistency Checks (ZMMJ)

    i compared the entries for SMMJ and updated for ZMMJ.

    The issue was resolved after the change.

    In addition add auth key SMMJ_02 for Auth object B_USERSTAT to the user performing the activity.

    thanks,

    sid

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 05, 2014 at 03:01 PM

    Hi Alam,

    have you fixed this issue??

    Actually we are facing same issue from last week. havent found any solution.

    Could you please tell solution which you have done to resolve this.

    Regards,

    Rahul

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Junaid Alam

      Hi All,

      We have the same issue, all tghe above comfig is in place, eventually we have raised the Oss.

      Meanwhile we get get rid of the error ny running report CRM_MESSAGES_DELETE (se38).

      Thanks

  • avatar image
    Former Member
    Jun 24, 2016 at 04:32 PM

    Hi Alam,

    It rarely happens to us also, especially when if the TRs are released with some errors in it or  when TR takes long time to actually import in target systems & solman does not wait for getting the TR status from this target systems.

    Thanks

    Add comment