We are planning an ERP upgrade from ECC 6.0, which has no enhancement package, to EHP 7.

Can this upgrade be done :

1. Directly to EHP7

OR

2. Do we need to first upgrade to a lower EHP, for example - to EHP 5 or 6 first, and then to EHP 7?

Thanks and Regards,

Reena

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • Best Answer
    Posted on May 19, 2014 at 09:35 AM

    Hello Reena

    It is possible to go directly to EHP7 but there are certain conditions.

    1 - Make sure the source system has the minimum SP level as per this SAP note 1942969 - table SFW_BF_SW does not exist on database

    2 - The system should be on a higher version of OS and DB if the target version is EHP6 and above.

    Check PAM for supported OS and DB for EHP7.

    https://service.sap.com/sap/support/pam?hash=pvnr%3D01200314690900005013%26pt%3Dt%257CPLTFRM%26ainstnr%3D012003146949000…

    Regards

    RB

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 19, 2014 at 09:14 AM

    Hi Reena,

    You can directly upgrade from ERP 6.0 to ERP 6.0 EHP 7 using SUM tool.

    Regards,

    Visu

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 19, 2014 at 09:17 AM

    Hi Reena,

    Yes, You can directly go to EHP7..

    1) Generate the stack XML file from solman as per your requirement

    2)check through PAM whether your DB & OS version is supported

    3) download latest SUM tool

    For more in details you can go through the Upgrade docs in SMP.

    Regards,

    Karthik.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 19, 2014 at 10:07 AM

    Hi Reena

    Yes, you can upgrade the system to ECC 6 EHP 6 or 7,

    before that is any other SAP system are connected to ECC6 ?

    If it is yes, Kindly refer the SAP Note, & you require to check those SAP version are supported to ECC 6 EHP 7 ?

    1388258 - Version Interoperability within the SAP Business Suite


    BR

    SS



    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 19, 2016 at 09:36 AM

    Hi Reena,

    I am in a similar situation like you. I have to upgrade our ECC 6 to ECC 6 EHP7.

    I am OK till Sandbox System, but how can we proceed in productive landscape. Do we have to perform same steps in DEV --> QAS --> PROD systems as well.

    If you could help and suggest me the best approach to achieve this task successfully, I will be very thankful to you.

    Regards

    Ahsan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.