Flexible Planning- RCCP material bottleneck

former_member183783
Contributor
0 Kudos

Hi,

I am trying to add 'component' as bottleneck for rough cut planning in flexible planning scenario. But when i choose 'material/production resource/tool' option below, there is a message ' no data existed for chosen selection ' . Any suggestion on it? thanks.

Configuration for the rough cut profile:

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

I have some question on SAP SOP

how did you disaggregate the data, I am seeing two portion top and bottom. How did you add macro to bottom portion?.

former_member183783
Contributor
0 Kudos

Qureshi:

If you configure the capacity ,it will show the capacity load...

0 Kudos

I have configured the capacity in days already. But I can't create macros such as "Carry over", "Backlogs" , "Buildable backlogs", "lost lot".

If you see the screen shot and let me know how to create this type of planning table in SAP rough cut planning
0 Kudos

I wanted to create planning table like in below in sap rough cut planning. Please take a look if you have any idea let me know