System allowing consumable budget to be more than current budget during budget transfer

Hi Experts,

        I am facing a very strange situation where consumable budget is more than current budget.This is ocurring during budget transfer via FMBB using prepost and then posting through work flow .

Before pre-posting

Current budget          300.000

Consumable budget  150.000

Consumed budget        7.000

Available budget        143.000

I Prepost two budget tranfer documents  documents for 150.000 each and eventually post.(If I try to prepost one document for 300.000 I get an error "The budget amount is not sufficient for release " which is okay).But if I split the amount into two and prepost they go through without any error.

After Pre-Posting

Notice current budget is now zero.

If I post the document instead of preposting , the system is checking fine and throwing an error after posting the first document but I can't post directly in production because we are using workflow.

I am missing any configuration ? Because this seems very illogical

Regards,

Lewis

FMBBBefore.png (3.5 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    May 13, 2014 at 07:21 AM

    Hi Experts,

        Have I posted in the right category?

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Lewis,

      There are several reasons for current budget not be the same as consumable budget.

      1. AVC ledger budget value filter setting in configuration. Please check your filter setting:

      Spro -> ......-> BCS -> Availability Control -> Settings for Availability control Ledger -> Define Filter Settings for Budget Values -> double click on  'Define Consumable Budget'. Check the setting for ledger 9H. Suppose your are using budget release senario. if no filter is set, all realeased budget is qualified as consumable budget while all budget is showing as current budget. If there is a difference between the amount of released budget and budget, the consumable budget and current budget can be different. Based on the situation you described (budget transfers updated current budget but consumable budget remained the same), I believe you use budget release, your filter setting is blank and the transfered budget has not been released yet.

      2. Data inconsistencies. This can be corrected by running FMAVCREINIT.

      Regards,

      Ming