Skip to Content
author's profile photo Former Member
Former Member

How does KNMA -execute target = actual allocation run?


Dear Experts,

Can anybody tell me how does KNMA run, what's logic inside?

Thanks!

Cindy

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on May 12, 2014 at 09:17 AM

    Hi,

    KNMA is for allocation of target and actual cost of cost centers to different cost object for the period. This is one way to distribute the values of cost centers.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.