on 05-05-2014 10:01 PM
Hello,
We have a schedule agreement we are trying to publish to ECC and getting the following error: "PurchSchedAgreement of object type could not be changed, 00004: No QM info record exists for material....".
The QIR exists for the Material/Vendor/Plant combination. The error is hitting on the last line item added in Sourcing. Why does ECC think the QIR doesnt exist? When it does.....Need to get past this error.
Thanks,
Jennifer
Edgar,
Thanks for all your suggestions! This issue has been resolved. The problem was with the revisions. We created additional QIRs for revision A,B,C. Revision D was already created.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jennifer,
can you confirm the material will correctly determine the QM batch, sample size, QM plan during goods receipt? Maybe it's not the QM record itself but another QM material configuration missing.
regards,
Edgar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Let's see, I'll list what I can remember now that could be a problem:
I think that's about it. If you could create a purchase order for that material and a goods receipt you could check at least if QIR is valid at today's date.
regards,
Edgar