MTO in PPDS

When I have run a product heuristic for a MTO scenario in Product view , it has raised a purchase requisition.Material procurement type is 'X' in product view.How is the priority determined?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • May 05, 2014 at 03:25 AM

    Hi,

    Procurement Type X - source selection is based on matching due date then priority then cost. If both In-house Production and External Procurement is possible then In-house Production (PPM) is chosen as source of supply.


    Best Regards

    Rui