Hi,

I am using 4 years Past and 2 years future in Dataview of a DP planning book.My requirement is Past period to be fixed as start week-01/2010 instead of 03/2010 as shown in the screenshot.It should not be rolling period.How to achieve this?

Thanks

Venkadesh

Capture.JPG (16.8 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jul 03, 2014 at 07:55 AM

    Hi Venkadesh,

    Just check the user exit for fixing the data .

    The user exit is PDATE.

    Regards,

    Mukesh Pandey

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 04, 2014 at 01:24 PM

    Hi Venkadesh,

    You just need to add the planning start date in Data View settings.

    Regards,

    JB

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Venkadesh,

      Go to the Planning Book and Data View Settings via t code /sapapo/sdp8b.

      Go to the required data view i.e. "XYZ". At Time buck profile Id , there is one checkbox for INPUT.

      Just un-select the checkbox the past period data view will be grayed out.

      Hope this helps.

      Regards,