Z Badi implementations are inactive after upgrade to ECC

bharatbajaj
Active Participant
0 Kudos

Hi SAP Folks,

We recently upgrade our one of the systems from 4.7 to ECC 6.0

And after the upgrade, the Z Badi implementations are inactive in ECC.

This is strange to see & I could not find the reason for this.

Also it will take ages to activate each Badi manually.

Any suggestions ????????

Thanks in advance,

Bharat Bajaj

2 REPLIES 2

Former Member
0 Kudos

That's happening when SAP delivers new implementations. Just go to SE18 and deactivate the SAP implementations and activate your custom ones.

You can identify them using

0 Kudos

Hi Daniel,

Thanks for your suggestion, but I will have to perform this activity for each Z implementation & there are so many... is there some way to activate them in single action. like some program or batch job to activate the multiple inactive BADI,

Regards,