Hi everybody,

I have created a user status for PM orders. the problem is when Order status in CNF ( confirmed ) and I use IW45 to cancel confirmation, the user status doesn't change to Release and still remain CNF. I couldn't find any business transaction for that.

what do you do for such case?

thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • author's profile photo Former Member
    Former Member
    Posted on May 01, 2014 at 02:34 PM

    Yes, there is no standard business transaction to set the User Status as Released.

    Change in status should be done either manually or through development using

    STATUS_CHANGE_EXTERN.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 01, 2014 at 02:57 PM

    Hello

    Its STD SAP behavior.Its strongly recommended do not change System status forcefully.

    Br

    Rakesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 02, 2014 at 12:51 PM

    but there is business transaction for canceling TECO.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 02, 2014 at 06:37 PM

    Is Business Transaction for cancelling TECO makes the user status into REL while cancelling Confirmation??

    Instead of giving short reply, give the complete details what exactly you are looking for.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 03, 2014 at 07:12 PM

    it's so weird SAP didn't consider any business transaction for that !!!!

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 04, 2014 at 05:55 AM

    From initial post, topic is about User Status change.

    Of course, System status will get changed accordingly from TECO CNF to REL CNF once TECO is cancelled. System status will get changed to REL CNF to REL PCNF once confirmation entry is cancelled.

    There are 3 of the user statuses such as REL, CNF & TECO. Once confirmation is done, CNF can be set using business transaction. Once TECO is done, user status TECO can be set using business transaction.

    If TECO is reversed, business transaction is available to set the user status from TECO to CNF. But if CNF is reversed, there is no business transaction to change the user status from CNF to REL.

    If you feel discomfort in using the given BADI, you can raise OSS with SAP.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      There could be many reasons why some of the expecting features are not available in standard SAP. Have you raised any OSS to SAP & have you got any replies??

      And, if you have concluded this query with using BADI for changing user status, suggest you to close the thread by marking correct or helpful answers, if you feel on any replies.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.