I am facing problem with distribution key . I have updated the Distribution key GLEI (Equal distribution) in Production version and the same has been updated in the BOM component. When I run product Heuristics in the PPDS system is creating one planned order in APO and Respective dependent demand. When that Planned order moved to ECC system, because of the Distribution key it is splitting the order quantity in the planned order duration equally, but it is not splitting the dependent demand of the Component.

I would like to know is there any prerequisites/ settings for the component to the dependent demand split. Your suggestions are highly appreciated.

Regards

Prabhakar Reddy

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear all,

Still the problem is not solved , I have referred this issue to SAP . I will update you  once SAP fix the problem .

Regards

Prabhakar

0 Kudos

Hi Prabhakar,

Please, check if this wiki helps.

Regards,

Tiago

Former Member
0 Kudos

Hi Tiago,

Thanks a lot  for your reply ... I tried this but  for one componet dependent requirements are not distributed , but it is working fine with the header material . I will check further and update you ..

Regards

Prabhakar

0 Kudos

Prabhakar,

Use heuristic SAP_PP_C001 for the planning and see the quantities get distributed for RMs.

Thnaks,

Rajiv


Former Member
0 Kudos

Hi Rajiv,

Thanks a lot  for your reply ... I tried this but  for one componet dependent requirements are not distributed , but it is working fine with the header material . I will check further and update you ..

Regards

Prabhakar