Apr 29, 2014 at 10:48 AM

Production Order Closure: Background Job

214 Views

Hi Team,

I am configuring the selection profile in BS42 for scheduling the background job for production order closure.

As principle, the order needs to be closed once the month end activities (like order is settled, order variance is calculated) are completed.

Once the variance is calculated for the order, the order will get the status "VCAL". But after the order is settled, the order will NOT get any status.

I need to select the orders for which the settlement is completed (order status ??) & variance is completed (order status: VCAL).

How to configure it in BS42?

Thanks