Hi Friends,
I have observed that whenever releasing the work order,irresepective of number of operations in the work order, system generating scheduling start and finish dates are same, however after releasing the Work order and by adding another operation in the work order, immediately scheduling end date equaling to Basic finish date (i.e.: Basic start and finish dates are equal to Schedule start and finish dates).
Can any body please explain why this is heppening
Please find the screen shots.
After adding one more operation in the operation list and save the Work order,then Basic start and finish dates are equal to schedule start and finish dates.
Regards,
Srinika