Partial deliveries in STO

495 Views

Hello,

I am rather new to MRP and ATP check. I have already searched the forum but i could not find how to solve this issue.

Can you please help me solve the issue below?

When we were creating outbound deliveries against STO, the deliveries were not appearing in transaction MD04.

Well sometimes the delivery appears in MD04 and sometimes it doesn’t.

In the material master, the strategy group defined was 00 - Noplanning / no requirements transfer

So we have added an additional entry in transaction OVZI, with source 1 - MRP type.



After this change in customizing, the deliveries started to appear in MD04.

However since this change, the deliveries are now being created in partial quantity (probably due to stock availability). The client doesn’t want to have partial deliveries they want only one delivery with total quantity.

I have checked the shipping details defined in the customer and it seems to be ok. Partial delivery are not allowed


Could you please help me prevent the creation of partial deliveries?

Thanks and regards,

Yannick