Capacity leveling onto working days

37 Views

Hi all -

We are trying to have APO demand planning schedule work on a day that is not a factory calendar work day. In ECC, we utilize the "Work Day Indicator" on the capacity to override the factory calendar to schedule work on days that are normally non-working days. In APO-SNP, the system correctly CIFs capacity on those days, but the capacity leveling function will not schedule work on them. It appears to be an disconnect.

How would we accomplish something like this without changing the factory calendar?