Dear All,
I am facing one issue on process order cost itemization level. I have maintained material origin(costing view 2) for all the raw materials in the material master. So that i am getting origin in the COR3 itemization.
Now when i check the COR3, system has to show raw material with planned, actual and variance. But system is showing two different lines for actual and planned.
So user facing problem at the time comparison of variance(planned-actual).
Please guide me as it is in production server issue.
Regards,
Prakash Javvadi.