Hi experts,
In scheduling planned orders (t-cd:OPU5), I set backward scheduling and start in the past as 999 days as below.
After sales order is created and MRP is run, system suggests forward scheduling date and time.
From my understanding, if the date scheduled by backward logic is over 999 days(set in start in the pat in OPU5), system suggests date scheduled by forward logic.
So I think "start in the past" in OPU5 does not work correctly.
Can anyone please kindly tell me how "start in the past" in OPU5 works how I set the configuration ?