Capacity evaluation for internal and external workers in one work center

99 Views

Hi ,

Normally in all Industries you have internal manpower to execute work. Say I have a work center named "Mechanical" , I will have 5 people working 8 Hrs for 5 days in a week. We usually configure this in capacity tab of work center for capacity category "002-Labour". In scheduling tab we configure sceduling data for a capacity category "002-labour"

In many industries , depending on load, many time, external labours are hired to give assistance to internal workers. Technically it is like adding one more capacity category "PER-Person" and adding number external labours there and in scheduling tab adding required configuration for "PER" capacity category

Total capacity for any given day would be available capacity in capacity category -002 + available capacity in PER capacity category.

However in scheduling Tab , scheduling basis can be either 002/PER.

How can we add more scheduling basis to refer to more than one capacity category ?

Any other alternative to above problem statement?