Skip to Content
0
Apr 24, 2014 at 05:58 AM

Process Message and PI sheet

381 Views

Dear All,

I have created one finished product and one raw material. In Master Recipe i created one Phase and assign two instruction category CONS_1 and PROD_1.

Now i generated PI sheet in COR2 and see CO53 that it is present and now i send it and in CO60 it is there.

Now when i see and enter quantity in PIsheet and double click on it to see the Process Message

1) PI_PROD has material number of finished product - It is ok

2) PI_CONS has also material number of finished product but it should have raw material number.

So, my issues are

1) How raw material will be there in PI_CONS Process Message.

2) Should i create two phase and assign it one by one or what else.

3) If i have Process Order of 500 quantity and through PI Sheet i do GR of 10 and GI of 10 then for next time how should i do GI and GR again. Should i send PI Sheet again from CO53 to CO60.

4) Is there only one control Recipe is generated for one process order.