Unable to close the project

Hi , I'm unable to close my project even after teco also. There are no commitments exists in the project. Error message is saying "There is still a purchase requisition commitment for WBS XXXXX". I have checkd PR and PO (ME5J, ME2J) reports also for commitments , but there are no commitments exists. Please suggest me if there is any SAP note for these PR related issues

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

6 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Apr 23, 2014 at 01:02 PM

    Hi,

    Check commitment in CJI5 report against that WBS also it's child WBS if available.

    Regards

    Shishir

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 23, 2014 at 01:52 PM

    Please check against CJi5 for the project, here you can identify the objects which have the PR's and PO's assigned to the project object.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 23, 2014 at 02:34 PM

    Hello Suresh,

    There may be inconsistencies in commitment which is appearing in the report even if there are no open commitments.

    Reason for this inconsistency is unknown.The inconsistency occurs because the period values of the totals tables COSP, COSS, COSR, COSL do not correspond to the totals of the corresponding line items COEP, COOI, COEPR, COEPL.

    In such case correction program RKACOR04 needs to be run for Object numbers of problem WBS elements in update mode.

    You can refer SAP note

    21649 - Comparison Totals records <-> Line items in CO


    Regards

    Tushar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 23, 2014 at 02:58 PM

    I have checked in CJI5 against WBS and its child WBS also. There is no commitments exists there .

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Suresh,

      Have you run correction report as I suggested you above. If not, please do that.

      We have also faced similar issue as mentioned by you earlier. After we run correction program RKACOR04 issue was resolved. You can also refer SAP note mentioned above.

      Regards

      Tushar

  • Posted on Apr 24, 2014 at 05:28 AM

    if you have done above solution then for data consistency CJEN is the transaction which will rebuild project database. then check all report if any open commitment is there for concern project or not?

    Regards,
    Sanjeev

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 24, 2014 at 06:04 AM

    Hello Suresh,

    You have indicated that you can't find the source of the commitment. Assuming there is one, run PS report S_ALR_87013533 and inspect the "commitment" column for non-zero values. The commitment value may be small - less than $0.50 - so switch report to 2 decimal places to check all values to the cent.

    If you do find the commitment, drill down to the line item report (click on "commitment" heading; go Goto > Call up report > line items) to identify and eliminate the PR/PO with the commitemnt value.

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi

      Please check this value is coming from which business transaction. Short close it if its a PR/PO or any other order is assigned then confirm it and close it. Once these values are nullified then do TECO to project again.

      NOTE: Please check the overall commitments independent of costs because generally we tend to execute report within specific dates/year and it does not bring the overall transaction history of costs.

      Regards

      Saurabh

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.