Apr 23, 2014 at 11:58 AM

MRP - Is it possible not to include stock that has already been used for planning in previous MRP Run.

31 Views

Hi all,

There's a business scenario where one wants to have control that if existing stock has been used for planning same shall not be available in next MRP run.

Existing Stock: Fabric - 1000m

Sales Order - 1567: required Fabric Qty: 600

MRP Run, Existing Stock is included : No Purchase Order is recommended

GRPO is created for fabric for 300mtr

second sales order is created where Fabric required is 800mtr

On MRP Run system shall display Purchase order only for 100 mtrs.

To summarize, is this possible to exclude the existing stock that has been consumed in previous MRP Run which has to be yet executed.

Thanks

Sonil