on 04-23-2014 4:41 AM
Hi,
In discrete manufacturing if we have alternate bom or routings then it can be used through production version. But in process industry it seems bom has to be created first and bom has to be assigned in production version and through production version master recipe has to be created for that.
In process industry let me know which master data has to be created first. Kindly clear my doubt.
Regards / US
Hi,
In process industry you can create BOM in both ways....
Method 1: Create BOM through CS01.... after this create master recipe... then you create Production version for the combination of BOM and recipe... same like in discrete....
Method 2: while creating master recipe you can create BOM from there during this process system will ask you for production version...
Now It is up to you to decide which one is flexible to use....
Thanks
Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.