Skip to Content
0
Apr 22, 2014 at 11:41 AM

Reg. Planning Calendar

37 Views

Hi All,

I have a doubt. I am using planning calender which has the setting of creating proposal on Friday of every week. This has been assigned to an finish good - X which has Procurement type F/30. It is procured from subcontrator. The lotsize used is an Z lot size which is a copy of PK. The MRP type also an Z MRP type which has category- NO MRP with BOM explosion.

The issue is when i create PR the Pur. req is not getting created on Friday for this material X.And it get created with some other day.

For eg. My requirement date is 10 Apr 2014. Hence according to planning calendar it should choose the requirement date as 11 Apr2014(friday) and it should create PR with the delivery date as 11 apr 2014. But in my case it gets created the PR with the delivery date of 10apr2014.I created PR from external system which creates in SAP via BAPI.

I suppose the planning calendar will be considered only when the material undergoes MRP run. If I manually create PR for the material X. Then it will not consider planning calendar right. Correct me if my understanding is wrong.

Regards,

MBN.