on 04-22-2014 6:08 AM
Dear Friends,
After creation of service PO the shipment cost is done and service acceptance is also done,can i change the shipment cost or i have to cancel it and create new document? accounting not done.
Regards,
jack
You can not change shipment cose document after acceptance.You need to cancel all follow on documents then change the Shipment cost document later follow Shipment Cost transfer process,Acceptance..etc.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To cancel service entry sheet follow below steps
1. Go to ML81N Tcode
2. enter your service entry sheet number
3. Go tochange mode
4. Unrelease service entry sheet by selecting Menupath Service entry
->Set Status -> cancel release
5. Then selct Menupath as Entry sheet -> delete
This will cancel service entry sheet.
Next step then VI02 undo cost transfer then you can change or delete the Shipment cost document.Before that check any invoice made against service entry in Purchase Order.