Hello SAP GURUS,
We are using Quantity Contracts in our SAP 4.7 Version, We had earlier faced an issue where requirements were being passed from Contract items to MRP where as they should not be passing to MRP,To prevent this from happening, we removed the Availabity and Requirement check for the concerned scheduled line category Z0 determined in our contracts through OVZ8,This stopped the requirements from being passed to MRP for the newer contracts after these changes went to Production but there are still requirements being passed to MRP for the older Open contracts created before these changes.
Now the Business would like us to prevent the requirements from being passed to MRP for the Old Open contracts, is there a way to prevent this, Appreciate your inputs on this.
Thanks and Regards
Mohammed Roshan