Budget transfer from one commitment to other commitment in FMBBC

198 Views

Dear Expert,

We are facing an issue with transfer of budget from one one commitment item to other commitment item.

below is the detail for commitment from where the budget needs to be transfer.

Now I can see in FMAVCR01 the amount is exactly same as per above

My client wants to transfer the Rs, 50,00,000.00 to some other commitment item. But while executing t-code FMBBC for transfer of budget with Auto Release system shows error message that Available budget is 4934510.28 is not sufficient to transfer.

The above amount is Current year budget (C) less Total Consumption (F).

Now my query is why system is considering only current year budget at the time of transfer with total consumption.

It should consider total budget (E) and less Total Consumption (F).

Will you please guide me on this.

Regards,

Prasad