Skip to Content
0
Apr 18, 2014 at 03:43 AM

How to create production version for multiple BOM & Routing ?

1355 Views

If I have 3 BOMs ( A, B & C ) and 2 Routing ( 1 & 2 ) for material XYZ then how then production version will be created ? I feel that there will be 6 PVs.

combination of A1, A2, B1, B2, C1 & C2. but some one told me that I have to create duplicate routing of 1 & 2

with number 3 & 4 and use it for bom B, and another duplicate Routing with number 5&6 and use it for BOM C.

in this case my PV data will be like this A1, A2, B3, B4, C5, C6.

Please guide me which way is correct. I feel that the first way is right, because in that case I have 2 routing in system, and in second way I have total 6 routings for that product. please guide me.