Hi,
After i run MRP with a weekly lot sizing procedure, avaiability date = start of the period, the MRP groups all planned orders of the week at the first requirements date of that week.
But what i need is to put that group of the planned orders in the last working day of the week before.
For example:
Week Friday Week n Week n+1 Ind. Requirements 0 1 1 1 1 1 Planned order 5Can you please help me how to solve this issue.
Thanks in advance.