Hi,
I have developed a program to short close PO (in mass). This program marks Delivery indicator and sets Latest GR Date.
After running this program POs are short closed and To be delivered qty/value shows zero in MM reports such as ME2N.
The problem is that this does not close commitments in Project. When I run PS report (say CJI5), I get those POs as open and the remaining values are still shown as open commitment in PS.
Please help me understand how to close this project commitment.
Regards,
UT