Project commitment shows even after closing PO

798 Views

Hi,

I have developed a program to short close PO (in mass). This program marks Delivery indicator and sets Latest GR Date.

After running this program POs are short closed and To be delivered qty/value shows zero in MM reports such as ME2N.

The problem is that this does not close commitments in Project. When I run PS report (say CJI5), I get those POs as open and the remaining values are still shown as open commitment in PS.

Please help me understand how to close this project commitment.