Cost rates maintained in ERP system and cost elements from PPM 5.0

Hello experts,

I will appreciate it if  you could help me with this subject below.

I want to search in ERP system what cost rates are maintained for each approved worked hour in PPM system. But, I do not know where should I look for this.

I take a look on the report of the created internal order:

You can see, that the actual posting of 25.000 is booking in the ERP PROD system on cost element IT-HOURS



   
When I display the booked working times I find 5 Hours taht I booked on my personnel number on Internal Order :


 
 

I want to know where in the system  is  maintained the cost rate that calculates automatically the 5 hours booked on cost element IT-HOURS to 25.000 . So each hour costs 5.000. I want to change the amount of each hour from 5000 to 50. 

I’m not an ERP expert so I don’t know where such rate can be maintained in ERP. I need your expert help!

Thanks a lot,

Ruxandra P.


 
 
 
 
 
 
 
 





1.jpg (10.7 kB)
2.jpg (22.2 kB)
3.jpg (21.9 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Apr 17, 2014 at 10:44 AM

    Hi Ruxandra!

    You have to change the rate for combination of sender costcenter and activity type. As I can see from the screenshot you have used the activity type "IT01".

    A good starting point is transaction code KP26 in ERP system to change the rates.

    Nevertheless it depends also on customizing of acitity types and CO, if actual rates are calculated or not.

    Regards,

    Peter

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 17, 2014 at 11:01 AM

    hi,

    As suggested, first step is to go to KP26 T-code, input the following:

    Version, From Period, To Period, Fiscal Year, Cost Center and Activity type.

    you will find here the cost for each hour, ERP calculates the labor cost wrt the labor hours on the confirmation multiplied with the value maintained under KP26.

    Hope this is helpful, let us know if any issue.

    thanks

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 17, 2014 at 01:16 PM

    Hello all,

    Meanwile I discovered this transaction! 😊 And you are correct with transaction KP26.

    But what I would like more now will be to understand why is this amount maintained there. Beacuse it not help me for what I need.

    Or maybe I still do not have a logical understanding of this field/amount.

    We used to thought that this costs are maintained in ERP on roles (I'm reffering at defined roles in PPM) . We have defined different roles with cost type, activity type and cost element.

    This below is one role from my structure and, on this structure we maintain different prices/hour for each role.

    Role type: Z001

    Role Name: It Project Manager

    Cost Type: Z_PM

    activity Type: IT-PM

    cost element: IT-Projmag

    And I want to know how could I customize this activity types and what would need to be done more in CO, to be sure that this rates are calculated as they supposed to be.

    Thanks for your reply!

    Kind regards,

    Ruxandra.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Hans-Peter Baier

      Hi Hans-Peter,

      Thank you for these very interesting posts.

      We are exactly facing the same issues.

      If I understand well, cost and revenue rates from PPM are used to manage plan costs in PPM. So when we customize them, it will be more for PPM purposes.

      In the other hand, we can within the ERP system rate for actual costs for activities in KP26. When activities are entered within CATS transaction, the number of units (hours / days) is mutiplied by the rate defined in KP26 and we obtain actual cost.

      Through PPM / ERP integration we manage to get actual costs from ERP into PPM. So we are happy from this side.

      Anyway our question is : why is there such a transaction in ERP customizing menu for PPM (transaction FINR3_CPROJECTS_CUST)

      Path : Collaboration Projects / Controlling / Assign Cost Elements and Activity Types

      Why does SAP proposes to associate a cost / revenue rate from PPM to an activity in SAP ERP like in the example attached.

      With all the elements gathered for up to now, we don't understand the use of such an information.

      Can you provide us with some elements of answer ?

      Thank you for your help.

      Cassoké & Yves