SAP WM Cutover

1339 Views

It is intended to implement SAP WM module at my company.

For the cut-over activities, is it possible to create a warehouse on the existing storage location with material stock?

i intend to adopt the following procedure

- issue the existing stock of all materials to a cost center

- send the transport for WM onto the PRD server

- extend WM views on the target materials

- create the storage bins for material placement in the system

- reverse the material issue document to bring the stock back

- place it in the relevant storage bin

Experts, I would like to inquire if the above mentioned procedure is ok?