Apr 17, 2014 at 05:23 AM

Issue in determination of planned delivery data in PR.

52 Views

Hello,

I have an issue in PR, where planned delivery time is picked wrongly. PR is created through MRP.

In info record, the planned delivery time is 8, in vendor master record planned delivery time is 0, and no contract exists. But when PR is created automatically through MRP, planned delivery time is 10 in PR. How is this possible, from where else does planned delivery time flow?

There are 4 materials in PO, among which 3 materials have pl.del time as 1 and for the fourth the time is 10, because of which when delivery is created for PO using VL10B, 3 materials are planned in one delivery and the fourth material is planned in another. Split in delivery is occurring. Statistical delivery dates are the same for all the four materials.

Please help e regarding this issue.

Regards,

Krishna Bharadwaj.