Dear QM Experts,

I have activated the Auto UD checkbox in Material master for a material.

When I create a Inspection lot & enter all the characteristics in QE53N, I select all & evaluate.

If all pass, then after evaluation - the lot shud automatically change to UD status sine Auto UD selected ?

However, the lot is still in rel status till we manually change it to UD to post goods mvmnt.

Pls guide me how to solve the above scenario so as the lot automatically changes to UD status after evaluating in QE53N (provided all data pass).