Skip to Content
0
Apr 16, 2014 at 07:49 PM

Delivery Schedule within the Firm Zone of a SA not firming

1491 Views

Hello,

We have delivery schedules within firm zone (defined in the Additional Data in item detail) of a SA but they are not firmed by MRP run.

Here is the material master setting and other relevant information:

MRP Type = PD (firming type = blank)

Planning Time Fence = 0 (in MRP1 view)

Not check the flag in OMIN to firm only the transmitted schedule line

Maintained Firm/Trade-off zone (as mentioned above) and Binding on MRP = '1' in an item of a SA

The delivery schedule supposedly be firmed based on the firm zone but is keep pushed out instead after MRP run.

I appreciate very much if you can tell what's causing the problem and how to remedy it.

Kind Regards,
Eddie